TOC3 Australia

From NOW to WOW in under 9 days 

BAE Systems Australia continues to break company record.

RAPID CCPM IMPLEMENTATION AND RAPID RESULTS USING EXEPRON - Andrew Kay

BAE Systems Australia implements Critical Chain Project Management to their Deep Maintenance Program of LIF Jets with amazing speed and equally amazing results.

 

AndrewBAE56

Presentation to the Exepron User Conference in Lafayette, Louisiana USA July 2015  Presentation Video

 

SummaryBAE

 

May 2015: 6 jets from 6, first time around on time and some up to 43% less time, a company record.

September 2015:  14 jets from 14, on time to requirement. The company record continues to tumble.

 

This is a remarkable result as the aircraft MRO environment is one of the most complex in which to deliver everything on time, to budget and to specification. What surprised BAE was the speed by which the knowledge and solution was delivered and successfully applied.

 

SimonM

 

The Critical Chain Project Management (CCPM) solution was fully installed in under 9 days.

First jet in project execution within 4 days, first results through the hangar within 2 weeks.

Some jets had up to 21% scope increase. 

 

TOC3 in collaboration with Danny Walsh, CEO of Exepron, provided the expert training and guided facilitation to the talented BAE team who quickly jumped on board with CCPM and grabbed onto EXEPRON with both hands. The software was used for both training, building the project networks in planning and runnning the Maintenance Program in real time.

 

Note: This is yet another TOC3 rapid implementation project where the solution was installed and operational within 10 days.

 

video

Exepron

exepron

Exepron is a unique multi-project Critical Chain Project Management Software solution with embedded real time intelligence to plan, schedule and execute projects.
Exepron answers the 7 most critical questions of project management in real time.
Contact us to find out how.

NEWS

PROJECT MANAGEMENT THAT DELIVERS30 DAY FREE TRIAL Synchronize 50 Projects 15 GB Storage Capacity Unlimited User Access Global Coll...
  ...

In a nutshell

Distribution Logistics – Inventory and Warehouse ManagementDo you want to dramatically improve Profits and Cash Flow?If you could get the right stock at the right place, in the right quant...
Integrity: Our word is our bond We do as we say We don\'t promise what we can\'t deliver and if for some reason we fail we apologise without delay and make goodOpenness We tell it...
Accelerate Productivity Improvement to Maximise Your Business SuccessBreakthrough business solutions designed, installed and operational within 10 working days.At TOC3 we work clos...
The TOC Expert (Jonah) DayMany of you have read Dr. Eli Goldratt’s best selling business novel “The Goal”. This inspiring work has been the foundation of business success for 1000’s ...
When we started out our clients were in the main small to medium manufacturing and project based businesses. We  are branching out into other specialised areas as our own consultin...
Special InvitationAs a business owner or senior manager your are cordially invited to a attend a business information seminar where you will learn about the Theory of Constraints (TOC), a b...
We got enough space now to play cricket”, \"Rework has virtually been eliminated\" Gigangit, Production Manager, Best Bar Reinforcements, Melbourne...
Are your projects running late and over budget? Do you have to trim the project specifications in order to meet budget or promised due date? Do resources become overstretched? Is there much ...
Our Guarantee:We guarantee to support you all the way until all agreed outcomes are fully achieved OUR PROMISE:Do what it takes to deliver the above.YOUR PROMISE:Do what it takes to remov...
The additional capacity generated by these systems creates the opportunity to boost sales revenue and maximise profits. If you want to go to the next level and boost sales rev...

Login Form



TOCICO

tocico_1

Certified Practitioners