TOC3 Australia

 Grant Johnston: Managing Director “That’s ******* amazing” Commenting on 75% reduction of WIP in under 3 weeks.

Brad Johnston: Operations Director “I’m very pleased with that” (known for his understatements) when seeing throughput increase by ~20% within 5 days of a 3 day solution implementation.

Jessie: Afternoon Shift Foreman, "Wow I like this system. My people on my shift no longer have to come to me to find out what to do next, the buffer boards show them”. Jessie: also said “Loading trucks and meeting delivery is now just so easy”

Rick: Day Shift Truck Loader was ecstatic “I can load 4 trucks now in the same time as 1 before that's incredible”

Dragi; Production Manager,“We were averaging 74 tonnes per day now that has jumped to 87 tonnes per day consistent”. (+18%)

Terry, Finance Director: “We have to wait a while before we can say we are making more throughput (a known conservative) but I can say we are making the same as before but so much more easily”.

Gigangit, Production Manager: “We got enough space now to play cricket"

video

Exepron

exepron

Exepron is a unique multi-project Critical Chain Project Management Software solution with embedded real time intelligence to plan, schedule and execute projects.
Exepron answers the 7 most critical questions of project management in real time.
Contact us to find out how.

NEWS

Download PDF version here...
No matter how you measure it, be it:more profitabilitymore cashshorter lead timesless inventorygreater capacityprojects delivered on time to budget an...
 Grant Johnston: Managing Director “That’s ******* amazing” Commenting on 75% reduction of WIP in under 3 weeks.Brad Johnston: Operations Direc...
Below is a small selection of results TOC3 practitioners have helped achieve for companies in Australia and New Zealand. In the following re...
REAL RESULTS - Fast, Safe and SustainableSince the early 1990’s companies around the world including Australia and New Zealand have been ac...

In a nutshell

  ...
TO COME - Viable VisionTurning your Top Line into your Bottom Line within 4 years - Guaranteed!...
“Some of the standout results (they are all standout, these are the real biggies) …I can sleep at night with the knowledge that the projects are where they should be and there is a wo...
The Goal – A Process of Ongoing ImprovementBy Dr. Eli GoldrattA new hero is winning the hearts and minds of American Managers.  The hero’s name is Alex Rogo, and thousands of executives...
From NOW to WOW in under 9 days BAE Systems Australia continues to break company record.RAPID CCPM IMPLEMENTATION AND RAPID RESULTS USING EXEPRON - Andrew KayBAE Systems Australia imple...
 We have a number of The Goal 3rd Edition in stock in Sydney at $45.00 each plus postage.PDF Review of the GoalTo order your copy now Contact Us   ...
Distribution Logistics – Inventory and Warehouse ManagementDo you want to dramatically improve Profits and Cash Flow?If you could get the right stock at the right place, in the right quant...
The Problem with ProjectsThe problem with projects is that all projects have problems. Some are more severe than others. When 4 out of 5 projects are reported to fail; either not delivered o...
“We have lowest ever late orders in our entire history. From 70% late 6 months ago to just 2 orders late last week.\" “We now have the platform to take off like a fighter from an aircra...