Stonewood Homes

ViAGO Client. TOC3 practitioner: Andrew Kay (Project Manager) & Andrew Cranwell. Credit to Phil Spitalney TOC Contractor.

Product: Custom Built Homes



  • Long lead time to build homes
  • Unhappy customers
  • Unhappy sub contractors
  • High Stress levels
  • Poor profitability

Action taken, changes made

  • On-site consulting project: Critical Chain Project Management
  • Installed Critical Chain based scheduling and Pipeline Management
  • Supervisors and Subcontractors trained to follow the new system



3 months after CC project installed


Lead Time to build standard 3 Br modern home

110 – 120 days Industry standard

73 Days consistent plus or minus 5 days

30% - 35% lead time reduced

Cash Flow

Not bad, sometimes going to 30-60 days.


Suppliers/contractors paid on time, and before time if they are in a tight spot.

Progress Payments


Reliable  on time

More projects hitting payment stages more regularly = predictable cash flow


Struggling to break even

Tangible difference.

As a volume business the ability to produce more = Better returns.

Customer Satisfaction

Lots of complaints

Lots of praise

One home on the market 2 weeks early (63 day build).

Contractor Satisfaction

Lots of complaints

Lots of praise for everyone

New levels of trust and payments on time

Stress levels

High – many sleepless nights

Much lower, ability to switch off and leave it to others.

Taken holidays for first time in years

New Zealand Press:

Tauranga Gets Gold! 

“Stonewood Homes, Matamata New Zealand enjoyed phenomenal success with two gold medals in the House of the Year Awards 2008.  They won the prestigious Category Winner and Gold Medal for their entry in the Homes $350,000 to $450,000 category.


“Some of the standout results (they are all standout, these are the real biggies) …

  • I can sleep at night with the knowledge that the projects are where they should be and there is a workable plan for the completion of the home.
  • Clients have a completion date that is real.
  • I have been away on holiday twice since the implementation of our project board, this has been without the need to take a phone for fear of the need for my direction. More importantly upon my return everything is still in order.
  • We have clients that are in their completed homes that consider us their friends after the process of building their home. They tell us their personal news and take delight in us sharing parts of our lives with them. This is a real breakthrough.”

Kevin Norris, Owner Stonewood Homes, Matamata, New Zealand





Exepron is a unique multi-project Critical Chain Project Management Software solution with embedded real time intelligence to plan, schedule and execute projects.
Exepron answers the 7 most critical questions of project management in real time.
Contact us to find out how.


Stonewood HomesViAGO Client. TOC3 practitioner: Andrew Kay (Project Manager) & Andrew Cranwell. Credit to Phil Spitalney TOC Contractor.Product: Custo...
The following client has achieved substantial results with TOC after Lean and some Six Sigma practices where already embedded in the organisation. So ...

In a nutshell

\"That’s truly amazing” Commenting on >75% reduction of WIP in less than 3 weeks and total elimination of back orders. Grant Johnston: Managing Director, Best Bar Reinforcements, Me...
Please note that some of the client results we report have been achieved whilst working in association with other TOC practices. We only report results here where our practitioners have had ...
How do we go about helping you get these kinds of Real Results?We do it by getting you to see that in order to have a breakthrough in performance the rules of business have to change.Manufac...
EXEPRON - Critical Chain Project Management Solution - 30 day Free Trial - sign up NOW!TOC3 are certified affiliates of EXEPRON.  We provide the necessary training and support to get yo...
Step 1: The best way to start is to do some reading and some background research.Almost everyone who goes onto transforming their business with TOC has read \'The Goal\' by Dr Eliyahu Goldratt...
“We were averaging 74 tonnes per day now that has jumped to 87 tonnes per day after only 8 days”. (+18%)Dragi; Production Manager, Best Bar Reinforcements, Melbourne...
“I have to spend less and less time on the factory floor trouble shooting and getting production to flow”“We have lots more capacity now that we are better organised and can schedule...
Our Guarantee:We guarantee to support you all the way until all agreed outcomes are fully achieved OUR PROMISE:Do what it takes to deliver the above.YOUR PROMISE:Do what it takes to remov...
1. PROBLEM DEFINITION: Understand Environment and agree on Core Problem to solve (2 - 5 days)We understand your environment - site audit We get to meet your key people and you get to know&nb...